Newsroom

The tender for the construction of the new Panathinaikos stadium was forced into a second protraction. According to information from ypodomes.com, the Municipality of Athens proceeded with a 15-day prolongation of the tender process, specifically from today, the 12th of the month, to January 27th. Three days later, on the 30th of the month, the tenders will be unsealed.

The reason the extension was given is a general technical hang-up that exists in the technical world. More specifically, since the end of the year, the degrees from the 3rd to 7th grade companies have expired. The solution will always be given according to the same information with an amendment that will be passed next week by the Parliament.

In fact, for the Municipality of Athens there was no alternative but to give an extension of two weeks in order to have the necessary time to settle the matter. Let’s remember that initially the competition was announced for December 13th and got a first extension for January 12th.

Funding and duration

The new stadium has been the dream of the fans of the “greens” for decades, but it is also related to the double reconstruction of Votanikos-Alexandras. The Commissioning Authority of the project is the Municipality of Athens. With the completion and operation of the new stadium in Votanikos, the current stadium on Alexandra Avenue will be demolished. The area there will be regenerated and shaped into a new large square, a green lung for the area.

The cost of the project amounts to an amount including VAT of 123 million euros (99.19 million euros without VAT). The project will be implemented using the study-build method. The project is financed for an amount of 115 million euros from the Public Investment Program (one of the largest proportionate amounts given for the creation of an infrastructure) and for an amount of 8 million euros from the Recovery Fund.

Essentially, the PIP will cover the construction of the stadium and the Recovery Fund, the urban regeneration of the former industrial area of Votanikos / Eleonas – Projects of landscaping and common areas in the area of Double Redevelopment and the Naval Fort in the area of Eleonas.

The duration of the projects is set at 36 months. In practice, the big goal is for the new Panathinaikos stadium to be operational in 2026 for the 2026-2027 season. The major groups of the country are expected to participate in the competition, while the possible participation of companies outside the borders will be of interest.

The project is one of the largest in the history of the Municipality of Athens and is part of the Double Redevelopment. In the next period, two additional projects related to the creation of network infrastructure (roads, pedestrian paths, drainage, electricity, telecommunications, water supply, etc.) and the general regeneration of the intervention area are expected to be auctioned.

The project also includes an amount of 3 million euros as an option for the construction of a pedestrian bridge with a budget of 3 million euros.

The object of the project

The subject of the awarded public project contract is the simultaneous study and execution (construction) of the project entitled “CONSTRUCTION OF A NEW FOOTBALL STADIUM OF PANATHINAIKOS IN VOTANIKO”.

For the construction of the project in question, the intended functional requirements and applicable specifications will be taken into account.

Also, the project is subject to environmental commitments according to the approved EIA.

In summary, the projects to be studied and built under the contract entitled “CONSTRUCTION OF A NEW SOCCER FIELD OF THE PANATHINAIKO IN STON VOTANIKO” are:

(a) The stadium itself (foundation, concrete etc.)

(b) The architectural and not only equipment of the field (roof, perimeter shell, etc.).

(c) The electromechanical facilities of the stadium (water supply, drainage, weak and strong currents, other electrical and mechanical equipment, etc.)

(d) The construction of the access road (open section and cut&cover with all their equipment), to the underground parking area of the stadium, as well as some accesses to the immediately surrounding area of the stadium

(e) Any necessary temporary traffic regulations during construction of the works.

The Object of the Project also includes the following:

  • The further investigations and studies in order for the Contractor to confirm the results of the available investigations and studies, to complete as many investigations/studies that need completion and to draw up the Final Study and the Project Implementation Study, in accordance with the requirements of the Project Studies and Investigations Regulation (KME) and the contractual documents of the Service as well as its Technical Offer Study.
  • The identification, recording, analysis and management of the risks of the Project, as well as all related work at the Design and Construction level to address them.
  • Any adjustments required during the preparation of the various stages of studies, due to a difference between the predicted conditions and the actual construction conditions of the Project.

ΜΗΝ ΞΕΧΑΣΕΤΕ

  • Ακολουθήστε το ypodomes.com στο Google News και μάθετε πρώτοι όλες τις ειδήσεις για τις υποδομές στην Ελλάδα
  • Αν είστε επαγγελματίας του κλάδου, ακολουθήστε μας στο LinkedIn
  • Εγγραφείτε στο Ypodomes Web TV