Historic moment for Greek Railways as Kiato – Aegio section reopens after a decade

Νίκος Καραγιάννης

Δημοσιεύθηκε

στις

A historic moment for northern Peloponnese was recorded earlier today, as the test route on Kiato-Aegio railway section was carried out successfully, with the presence of the Minister of Infrastructure and Transport, Mr. Christos Spirtzis, the General Secretaries of the Ministry and many other officials that have been involved in this major project. The line is under upgrade as part of a project that covers Kiato-Rododafni section. 

The new line is now completed, as ypodomes.com reported last week, however pending signaling works temporarily obstruct the operation of the new section, which, according to railway executives, is postponed until the end of the Summer.

Another question to be answered is whether the line will operate as a suburban or as an interurban route, considering that the new section from Kiato to Aegio is not yet electrified. The same executives told ypodomes.com that, currently and in cooperation with TRAINOSE, different scenarios concerning the operation are being examined. The 3 dominant options are: 1) the launching of a diesel-powered train from Athens to Aegio 2) an electric train from Athens to Kiato, switching to diesel trains at Kiato Station and 3) a combination of both itineraries on a daily basis.

The new double-track line with its operation is expected to boost growth across the coastal front of northern Peloponnese, bringing the modern train just 35 km outside the city and the port of Patras.

The projects on the newly-released section will be completed with the installation of the electrification systems. This project has a budget of 68m euros and is now in its final auction phase. It is estimated that the contract will be signed in June 2019. The construction period is set at 30 months.

 

Nikos Karagiannis-ypodomes.com

Follow Nikos Karagiannis on Twitter and Linkedin

image_pdfimage_print
συνέχεια ανάγνωσης

News in English

Railway works from Aegion to Patras become a «Gordian knot»

Νίκος Καραγιάννης

Δημοσιεύθηκε

στις

Σιδηροδρομικός Σταθμός Αιγίου

With mutilple issues in the construction sector, the new Infrastructure Minister, Mr. Kostas Karamanlis, will be called upon to take a number of serious decisions.

One of the «time bombs» that he should definitely disarm, or otherwise described, a «Gordian knot» to be solved is the issue of the railway contracts that will bring the train to Patras and more specifically, on Aegion-Patras section.

Infrastructure works are currently running from Aegion to Rio today, while there are three contracts under development that are due to expired by the end of 2023.

If the county fails to meet the above deadline, there will be a serious risk for the reimbursement of all funds received from NSRF for the entire Athens-Patras corridor, back to the EU.

The irony here is that the funding is not the No. 1 problem but the fact that the necessary projects have not yet been auctioned, while we are already in the second half of 2019.

The necessary works

The two contracts from Aegion to Psathopyrgos and from Psathopyrgos to Rio, concern superstructure works, electrification, signaling, train control systems and stations’ construction works.

At this time, the Large-scale Project Envelope matures so as to be approved by DG Regio. Here, even marginally, we can anticipate completion of these projects, by the end of 2023.

But the situation is far more serious regarding the contracting between Rio and Aghios Dionysion, in the centre of Patras. This project has been designed to be fully underground at a length of 5 km.

In fact, the project was announced to be auctioned in early 2019 with an initial cost of 400m euros, likely to double, making it doubtful for the EU to finance it.

Many scientists have previously expressed their opposition to the full undergrounding of the line due to the unstable subsoil that can cause a large financial burden and large technical challenges.

However, what is crucial is that the modern, electric train to reach Patras one way or the other by the end of 2023.

Works on Kiato-Rio railway line

At this time there are three contracts that are underway from Kiato to Rio. The first concerns the «broom contract» from Kiato to Aegion, which has reached its trial phase and is expected, at some point, to enter commercial operation.

Nevertheless, the almost completed double-track line even though will be released with new stations, is not yet electrified. For this project there is a tender in progress since last year and the contract is estimated to be signed over the coming period.

image_pdfimage_print
συνέχεια ανάγνωσης

News in English

Electrification goes live in northern Portugal

ypodomes team

Δημοσιεύθηκε

στις

από

Σιδηροδρομικός σταθμός με ηλεκτροκινούμενες γραμμές

Prime Minister António Costa and Housing & Infrastructure Minister Pedro Nuno Santos attended ceremonies on July 16 to mark completion of two electrification schemes on routes north of Porto. Both projects are part of the government’s Ferrovia 2020 investment plan.

A 14·2 km section of the Porto – Pocinho Douro Valley line has been wired at 25 kV 50 Hz between Caíde and Marco de Canaveses at a cost of €10·5m.

This will enable the Porto suburban network to be extended as far as Marco de Canaveses. Electrification of the rest of the line has been proposed, but for now passengers continuing up the valley on the popular tourist route towards Régua and Pocinho will need to change to connecting DMU services at Marco de Canaveses.

A 44 km section of the Minho line between Nine and Viana do Castelo has also gone live. This forms part of a wider upgrading of the Porto – Vigo route which crosses into Spain. Electrification has been undertaken at a cost of €16·5m and paves the way for direct inter-city trains between Viana do Castelo and Lisboa.

Regional services to and from Porto are to be accelerated by around 12 min, while the Porto – Vigo journey time is expected to fall by around 10 min thanks to investment in track renewals and resignalling. This is also intended to allow 750 m long freight trains to use the route.

Electrification work is already underway over the 48 km between Viana do Castelo and Valença on the border with Spain.

 

Source: railwaygazette.com

image_pdfimage_print
συνέχεια ανάγνωσης

News in English

Crete: Proposal for the introduction of electrified railway, under consideration

Νίκος Καραγιάννης

Δημοσιεύθηκε

στις

Σιδηροδρομικός σταθμός με ηλεκτροκινούμενες γραμμές

For the very first time in the modern history of Crete, the discussion for the development of a railway that will reinforce transports in the island, linking its main cities, begins in the form of studies.

During a meeting of the Environmental Committee of the Region of Crete, held yesterday, the proposal for the introduction of a railway axis on the island was examined. The proposal was made by the Deputy Regional Chief for the Environment, Mr. Nikos Kalogeris, who noted that he intends to start a relevant survey (apparently icluding viability and cost efficiency studies) for a fixed-track, electrified means of transport, running along Crete  island.

The construction of a railway in Crete has been a long-standing issue, as the relevant conversation has begun since 1880, without ever being able to proceed. From time to time proposals have been presented, that always ended up in the drawers of ministries and local authorities.

image_pdfimage_print
συνέχεια ανάγνωσης

Facebook

Ετικέτες

δημοφιλη θεματα